Hunan Yongzhou Mahuangtang Energy Storage Power Station
Location / Time
Yongzhou City , China / 2021.11
Installed Capacity of the Project
Project Type
Utility-Scale Power
Introduction
The project is China's first large-scale grid-side station adopting a modular parallel energy storage system. Based on JDEnergy's modular energy block storage solution, after nearly one month of on-site testing, the project successfully passed all 18 stringent tests on the first attempt, with performance surpassing national standards, including low/high voltage ride through, primary frequency regulation, hertz response, source-grid-load coordination, AGC/AVC, power quality, dynamic response time and system efficiency. This milestone marks a comprehensive technological breakthrough in multi-module parallel cluster control, ride through performance and resonance suppression.